TCEL Schedule & Progress Report — DNIC National Connectivity Programme
As of Week 68 · Aug 2026Source: NCP8 schedule tracker (301 sites)
Overall progress
88.4%
Plan called for 100% by W40 — 11.6 pts behind
Sites fully completed
120/ 301
39.9% of all sites — FO + GPON both live
FO cable pulled
293/ 301
97.3% of sites ready for GPON
Districts at 100%
3/ 13
Aileu, Ainaro & Liquica fully closed out
F8 cable installed
94.1%
250,438 m of 266,000 m contracted
Fixing-100 rework
83/ 100
Locations re-fixed to date
Cumulative progress — Plan vs Actual
Weighted across all project phases, week 0–68
Plan (target)
Actual (achieved)
Site installation status
301 sites, FO + GPON rollout
Progress by project phase
Share of each phase's own scope completed · weight = share of total project
Sites completed by district
Bar length = number of sites · sorted by completion
Completed (FO+GPON)
FO done, GPON pending
FO in progress
Cable & material progress
Realised vs contracted
ADSS cable116%
312,000 m realised / 268,000 m contracted
Figure-8 (F8) cable94.1%
250,438 m realised / 266,000 m contracted · 15,562 m remaining
Fixing-100 locations83%
83 of 100 flagged locations re-fixed
Near-term milestones
Highlighted activities, July–August 2026
Generated from “120826_NCP8 Report TCEL Schedule Progress Report — 301 Sites” · figures reflect the workbook's own Plan/Actual formulasDashboard built for internal monitoring