← Back to dashboard

Network Deployment Task Log

Activities in October & CISCO/ALLOT core-network tasks

Activities in October

DO/Inspection
DO Fs.com
Oct 15, 2025
Done
Fiber optics(Cables ADSS & F8) - part 1
Oct 17, 2025
NY
DO Vmware
Nov 7, 2025
NY
Fiber optics Materials - part 2
Oct 24, 2025
NY
DO Cisco & Allot
Oct 8, 2025
Done
DELIVERY and Psyhical Installation
Fs.com to Districts
Oct 24, 2025
NY
Fiber optics(Cables ADSS & F8) - part 1
Oct 17, 2025
NY
Fiber optics Materials - part 2
Oct 24, 2025
NY
CISCO & ALLOT
Oct 10, 2025
Done
WAN Equipments
Oct 17, 2025
Done
INSTALLATION
Cisco Installation
Oct 9, 2025
Finishing
Allot Installation
Oct 10, 2025
Finishing
Solarwinds
Sep 18, 2025
NY
Fiber optics and suppoting Material
Sep 27, 2025
NY
WAN
Oct 20, 2025
NY
GPON
Oct 17, 2025
NY
TRAINING
SOLARWINDS
Aug 28, 2025
Done
GPON
Oct 20, 2025
Done
Fiber Optics
Dec 15, 2025
Done
CISCO & Allot
Nov 5, 2025
—
UAT
ReUAT Solarwinds
Oct 16, 2025
Done
UAT Cisco & Allot
Oct 31, 2025
NY
UAT VMWare
Nov 20, 2025
NY

CISCO and ALLOT

INNITIATION/INCEPTION
PO/Project Award SPV Module - part 1
—
Done
PO/Project Award - part 2
—
Done
HW Ordering & Arrival
—
Done
DEFINITON
Internal Kick Off
—
Done
External Kick Off
—
Done
Assesment / Technical Requirement
—
Done
BUILD
Build & Submit LLD & MOP
—
Done
DRM & Approval (onsite)
—
Done
Staging & Preconfig on NTT Warehouse
—
Done
HW Delivery to Dili (NTT Wh to TCEL Wh)
—
Done
HW Check/Inspection by Tcel
—
Done
HW Check/Inspection by DNIC
—
Done
DEPLOYMENT (Onsite)
Hardware Installation
—
Done
Hardware Configuration & Integration
—
Done
Migration
—
Done
Monitoring
—
Done
Documentation
—
Done
Hardware Installation (2 Switch per day)
—
Done
Hardware Configuration & Integration (2 Switch per day)
—
Done
Migration (2 Switch per day)
—
Done
Monitoring (H+1)
—
Done
Documentation (H+1)
—
Done
Hardware Installation
—
Done
Hardware Configuration & Integration
—
Done
Migration
—
Done
Monitoring
—
Done
Documentation
—
Done
Hardware Installation
—
Done
Hardware Configuration & Integration
—
Done
Migration
—
Done
Monitoring
—
Done
Documentation
—
Done
Hardware Installation
—
Done
Hardware Configuration & Integration
—
Done
Migration
—
Done
Monitoring
—
Done
Documentation
—
Done
Hardware Installation
—
Done
Hardware Configuration & Integration
—
Done
Migration
—
Done
Monitoring
—
Done
Documentation
—
Done
Supervisor Installation & Upgrade Chassis Firmware (2 Location)
—
Done
Supervisor Installation & Upgrade Chassis Firmware (2 Location)
—
Done
Hardware Handover
—
Done
UAT
—
Done
CLOSING
Transfer Knowledge
—
Done
ABD UAT Review & BAST Signing
—
Done
NCP8 · 301 Sites — live data, TCEL Schedule & Progress tracker